PROJECT TITLE
Grand Opera House, Belfast
Project Overview
A challenging project that involved modification of the existing plant room and air handling units.
Description
The existing plant room and kitchen were decommissioned before works commenced. A new gas line was installed to provide a Natural Gas supply to the new plant room layout and air handling units. A new Gas Detection System was designed and installed for the new plant room layout and air handling units as required.
EB Gas coordinated with the main mechanical contractor, Hanna Mechanical, and the main building contractor, Tracey Brothers, for the duration of this project.
Date of Completion
The project was completed during working days and weekends over 16 weeks.
back